New High-Voltage Installations (Capacity Upgrades, Temporary Power Supply)

Source:https://rc.whrcfzjt.com/whIndex/#/whIndex Updated:2026-05-19 15:30 Hits:

Acceptance Conditions

1. For high-voltage new installation or capacity upgrades services that involve two or more multi-circuit power supply routes, fees for high-reliability power supply shall be charged in accordance with:the Forwarded Supplementary Notice on Issues Concerning the Cessation of Collecting Power Supply and Distribution Connection Fees (Wan Jia Fu [2024] No. 223), and the Letter of Anhui Provincial Price Bureau on the Issue of Charging Standards for High-Reliability Power Supply Fees at the 20 kV Voltage Level (Wan Jia Fu [2011] No. 131).

2. For projects within the urban planning boundary that have obtained land use rights after March 1, 2021, a cost-sharing mechanism for power access engineering outside the regulated property redline, jointly borne by the government and the power supply enterprise, has been established. Specific cost-sharing shall be implemented with reference to local regulatory documents.

3. The approval document for the power usage project refers to the project approval, ratification, or filing documents issued by the relevant government authorities as required by national regulations such as the Administrative Measures for the Verification and Filing of Enterprise Investment Projects.

4. Relevant information on design, construction, and equipment/material suppliers can be queried through channels such as: Credit Energy website (http://xyny.nea.gov.cn/publicity) National Public Service Platform for Market Supervision of Construction (http://jzsc.muhurd.gov.cn/data/company)

5. If you opt for a two-part tariff, the billing method for the capacity/demand charge must also be confirmed simultaneously. Should you need to modify it, the change for the billing cycle three months later must be processed at least 15 working days in advance.

6. Materials obtainable through data sharing with government departments are exempt from submission.

7. Documents previously provided and still within their validity period are not required to be submitted again.

8. Any newly installed or replaced transformers must comply with the Grade 1 or Grade 2 energy efficiency standards as stipulated in Limited Values of Energy Efficiency and Energy Efficiency Grades for Power Transformers (GB 20052-2020).

Processing Sites

This service is available for online processing from start to finish.

For in-person service, all Wuhu business halls are available, as listed below:

1. Chengbei Business Hall(Daqiao);

Address: 80 meters west of the intersection of Huashan Road and Xiangyang Road, Jiujiang District.

2. Zhongshan Bei Road Business Hall;

Address: 25 Zhongshan Bei Road, Power Supply Building, 1st floor.(Next to the Wuyue Plaza).

3. Chengdong Business Hall;

Address: 8 Xiangtai Road, Jiujiang District.(Opposite to Dongziyuan).

4. Chengnan Business Hall;

Address: 7 Zhanghe Road, Yijiang District.

5. Qingshui Business Hall;

Address: Approximately 60 meters southeast of Wuhu Qingshui Middle School, Huangshan East Road.

6. Jiangbei Business Hall;Address: Yongnan Street, Erba Town, Jiujiang District (Beside Tongjiang Avenue).

Inquiry Hotline

0553-3807000

Processing Method

Method1: Anhui Government Services Web: https://wh.ahzwfw.gov.cn/

Method2: State Grid Online(Wang Shang Guo Wang) App

Required Documents

1. Proof of Eligibility for Electricity Application.

For individuals: A valid identity document (e.g., ID Card, Military ID, Passport, Household Register, or household registration certificate from the public security organ).

For organizations: The legal representative's valid identity document, and the Business License or Organization Code Certificate, Registration Certificate, or supporting documents issued by the competent authority.

2. Proof of Property Rights for the Electricity Usage Address.

Documents such as the House Ownership Certificate, Land Use Right Certificate, or other proof of legitimate property rights issued by the township (sub-district, village) level or above government, or by the competent housing, urban construction, or land management authorities within their jurisdiction.

3. Approval Document for the Power Utilization Project.

4. List of Electrical Equipment.

If you authorize another person to handle the application, a valid identity document of the agent and a Power of Attorney must be provided simultaneously.

For applicants with incomplete materials, a "Tolerant Acceptance" service will be provided as long as the Proof of Eligibility is submitted. The applicant must provide the missing materials during the subsequent on-site service visit.

Process Flow

For Standard Users:

Business Acceptance → Power Supply Plan Reply → Final Inspection, Meter Installation & Power Connection

2. For Key Power Users:

Business Acceptance → Power Supply Plan Reply → Design Document Review → Intermediate Inspection → Final Acceptance and Meter Installation & Power Connection

Commited Timeframe

1. After accepting your electricity application, we will schedule a site survey with you to assess the power supply conditions. You will receive the power supply plan within 10 working days (20 working days for dual-power supply users).

2. The power supply plan remains valid for one year from the date of your acknowledgment. If special circumstances require an extension, you must submit an application at least 10 days before the expiration date.

3. For key power users, to ensure engineering compliance, we provide a design document review service. You must submit the design unit's qualification certificates, along with the design and specification documents for the power reception project. Upon fulfillment of requirements, the review will be completed within 3 working days, and a Customer Power Reception Project Design Document Review Feedback Form will be issued. Any problems identified during the review are supposed to be promptly rectified, and the resubmission procedure will be followed after the rectification is completed.

4. For key power users, to ensure construction meets electrical safety requirements, we provide an intermediate inspection service. Before covering concealed works such as cable trenches and grounding grids, please notify us promptly for inspection. You must provide the construction unit's qualification certificates and records of concealed works and tests. Upon fulfillment of requirements, the inspection will be completed within 2 working days, and a Customer Power Reception Project Intermediate Inspection Feedback Form will be issued. Any problems identified must be promptly rectified, and the re-inspection procedure will be followed after the rectification is completed.

5. For the power reception project under your responsibility, please independently select qualified design and construction units to carry out the design and construction.

Upon project completion, please submit a completion inspection application along with materials such as the project completion report (including as-built drawings).

We will complete the final inspection within 3 working days and issue a Customer Power Reception Project Final Inspection Feedback Form.

Any problems identified must be promptly rectified, and the re-inspection procedure will be followed after the rectification is completed.

Once the power reception project passes inspection, the electricity supply contract and related agreements are signed, and reliability fees are settled according to government-approved pricing, we will proceed with meter installation and power connection within 3 working days.

Implementing Body

State Grid Anhui Electric Power Company Limited

Policy Basis

Forwarded Supplementary Notice on Issues Concerning the Cessation of Collecting Power Supply and Distribution Connection Fees (Wan Jia Fu 〔2024〕 No. 223); Opinions of the National Development and Reform Commission and the National Energy Administration on Deepening and Enhancing the "Access to Electricity" Service Level to Comprehensively Build a Modernized Electricity Business Environment (Fa Gai Neng Yuan Gui 〔2025〕 No. 624) ; Letter of the General Office of the State Council Forwarding the National Development and Reform Commission and Other Departments' Opinions on Cleaning up and Regulating Charges in the Urban Water Supply, Power Supply, Gas Supply, and Heating Industries to Promote High-Quality Development of the Industries (Guo Ban Han 〔2020〕 No. 129); Notice of the Anhui Provincial Development and Reform Commission, Department of Finance, Department of Housing and Urban-Rural Development, Department of Natural Resources, and Administration for Market Regulation on Issuing the "Implementation Plan for Cleaning Up and Regulating Charges in the Urban Water Supply, Power Supply, and Gas Supply Industries to Promote High-Quality Development in Anhui Province" (Wan Fa Gai Jia Ge 〔2021〕 No. 543); Notice of the Anhui Provincial Development and Reform Commission and Anhui Provincial Energy Bureau on Further Improving the "Zero Investment" Policy for Power Access Projects to Create a First-Class Business Environment (Wan Fa Gai Jia Ge Han 〔2022〕 No. 93); Administrative Measures for the Verification and Filing of Enterprise Investment Projects